'The Rink' is NOW OPEN! Find more info and purchase $5 Skate Rentals HERE.

News

2020 maintenance program begins June 25th

Bourbonnais, IL - In an ongoing effort to improve and update necessary infrastructure throughout the village, the annual MFT (Motor Fuel Tax) street maintenance and curb replacement program will begin Thursday, June 25th with the following areas included:

  • Highpoint Circle S
  • Latham Dr.
  • Notthingham 
  • Jones Dr.
  • Washington Ave.
  • Edgemere Dr.
  • Meadows Road S
  • Vantage Lane
  • Tower Rd.
  • Plum Creek Dr.
  • Ray Street

Weather-pending, the tentative construction schedule is as follows:

  • June 25th - 29th Concrete removal and replacement
  • June 30th - Landscape
  • July 1st - 2nd Grind/chipping
  • July 6th - 8th Paving/priming

Notices will be provided to residents impacted by the improvement project. There will be no parking along the roadways during construction. Access to homes will be maintained during concrete removal and replacement. There may be instances where direct access is temporarily unavailable during the pouring of material. 

We ask that all motorists please use caution the above noted areas. As always, we thank you for your patience. Updates will be provided as they are available.

VIEW STREETS

VIEW MAP